Edit page
Construction
Construction Updates

Roof- Central Heating Plant & South Classroom Building

Last Updated: Wednesday, February 20, 2019

Status: Construction Phase

DESCRIPTION AND BACKGROUND:
The roofs at the Central Heating Plant and the South Classroom Building need replacement. As part of a capital "Building Envelope" project, these two roofs are phase one of the larger project.

UPDATES:
The roofs have been replaced and are complete.

FACTS:

Estimated Cost: $700,000
Estimated Date of Completion: Summer 2018
Architect: Mosaic Architects, Troy NY
Construction Manager: Lyle Nolan, SUCF Project Manager
College Representative: Jeff Lewis, Campus Architect
Contractor: NUA Construction Corp. Ardsley NY
Source of Funding: capital