Construction Image

Construction Updates

Capen Student Rooms

Last Updated: Monday, October 28, 2013

DESCRIPTION AND BACKGROUND:
The student rooms in Capen Hall will be renovated over the summer 2013.

UPDATES:
All student rooms in Capen Hall have been renovated to include new floor tile, new ceilings and paint.

FACTS:

Estimated Cost: $1,000,000
Estimated Date of Completion: August 2013
Architect: Megan Smailer, Campus Architect
Construction Manager: Kemp Anderson, Project Manager
Contractor: Asbestos- Two Brothers, Painting- Karavias, Flooring- Continental
Source of Funding: DIFR