DESCRIPTION AND BACKGROUND:
The existing electrical distribution lines campus wide are deteriorated and need to be upgraded in preparation for new building structures in the future.

UPDATES:
A study has been done on the current system and recommendations have been made. C&S Engineers have been working on the design which is about 60 percent complete at this time.

FACTS:

Estimated Cost: $12,017,000
Estimated Date of Completion: May 2013
Architect: C&S Engineers
Construction Manager: SUCF
College Representative: Brian Pine, Dir. Facilities Operations / Gary Buckman, Asst. Dir. FOC
Contractor: to be determined
Source of Funding: SUCF/Capital