DESCRIPTION AND BACKGROUND:
The existing electrical distribution lines campus wide are deteriorated and need to be upgraded in preparation for new building structures in the future.
UPDATES:
A study has been done on the current system and recommendations have been made. C&S Engineers have been working on the design which is about 60 percent complete at this time.
FACTS:
| Estimated Cost: | $12,017,000 |
|---|---|
| Estimated Date of Completion: | May 2013 |
| Architect: | C&S Engineers |
| Construction Manager: | SUCF |
| College Representative: | Brian Pine, Dir. Facilities Operations / Gary Buckman, Asst. Dir. FOC |
| Contractor: | to be determined |
| Source of Funding: | SUCF/Capital |